Bird & Bird Energy News July 2012


DECC announces decision on Transmission Constraint Licence Condition


DECC announces decision on Transmission Constraint Licence Condition

On 16 July, the GB energy ministry DECC announced its decision on a Transmission Constraint Licence Condition (TCLC), intended to prohibit generators from exploiting periods when there are transmission bottlenecks. The TCLC is now before Parliament for approval, and the intention is that it should come into force on 29 October. The drafting of the TCLC leaves a number of important issues unclear, but market participants must wait until the TCLC comes into force for Ofgem’s revised guidance.


The Energy Act 2010 gave DECC a power to impose a condition in generators' licences, limiting their ability to exploit periods when there is insufficient capacity to transmit electricity from where it is generated to where it is consumed. During such periods, National Grid, as system operator, must balance the system by paying generators to increase generation, or accepting a payment from them or paying them to reduce generation (to be “constrained off”). In some situations, National Grid has been required to pay significant sums to generators to do this. These costs are ultimately borne by consumers. The energy regulator Ofgem has long been concerned about this situation, suspecting that some generators have even sought to create or exacerbate transmission constraints. It has unsuccessfully attempted to use its competition law powers to address this type of conduct. DECC considers that a specific licence condition will also give greater clarity than tools such as the Regulation on Wholesale Energy Market Integrity and Transparency, REMIT. In December 2011, DECC consulted on a proposal to exercise its power to impose a licence condition, and Ofgem consulted on proposed guidance on the enforcement of the condition.


The proposed licence condition will prohibit 2 types of conduct:

 

Where a generator creates or exacerbates a transmission constraint by deciding to generate or not to generate with a particular plant when it had more economic options available to it, and then seeks or charges an excessive price for reducing or increasing generation in the Balancing Mechanism (BM), from its notified position; and
Where a generator exploits a period of export transmission constraint (where there is more generation within an area than can be transmitted out of it) by paying or bidding to pay excessively low amounts to reduce its generation, or by being paid or seeking to be paid excessively high amounts (ie. negatively-priced bids) to reduce generation. It should be noted that there is no comparable prohibition on excessive pricing during period of import constraints.


DECC decided not to proceed with its proposal to include in the TCLC the charging of excessively high amounts for the arming of inter-trips - devices allowing National Grid to trip a generating plant off the transmission system automatically.


Although the final version of the TCLC makes a number of improvements to the wording of the consultation draft, some of the deficiencies remain. For example, the TCLC continues to treat as the creation or exacerbation of a constraint the despatch or withholding of generation when the licensee had more economic options available to it – irrespective of whether those other options would also have created or exacerbated the constraint. In addition, the drafting does not reflect entirely accurately a number of the technical definitions relating to the operation of the BM and transmission constraints.


DECC explains that Ofgem will issue revised guidance on the date on which the TCLC comes into force. Given the lack of certainty in the TCLC itself on a number of key issues, including the question of when a price is “excessively” high or low, it is unsatisfactory not to have definitive guidance sooner.

Breach of the TCLC will be penalised in the usual way, with Ofgem having the power to impose a penalty of up to 10% of the licensee's turnover. However, in this case an appeal will lie to the Competition Appeal Tribunal. The appeal will be a rehearing on the merits rather than merely a review of the legality of Ofgem's decision.


Comment


The TCLC will impose significant obligations on generators in constrained areas – currently mainly in Scotland but potentially also in other areas as more generation is developed in remote areas. Each dispatch decision will need to be carefully weighed against other potentially more economic options, and bids will need to be priced carefully by reference to avoidable costs. The practice of high-priced "sleeper bids" will come under close scrutiny. One question that remains unanswered at this stage, however, is whether the TCLC will have the unintended consequence of deterring generators (in particular flexible generators) from bidding into the BM at all, so as not to risk accusations of breaching the prohibition, and thereby reducing the options available to the system operator to balance the system.


Contact Us

 

For more information please contact:

Peter Willis

peter.willis@twobirds.com


The content of this update is of general interest and is not intended to apply to specific circumstances. The content should not, therefore, be regarded as constituting legal advice and should not be relied on as such. In relation to any particular problem which they may have, readers are advised to seek specific advice. Further, the law may have changed since first publication and the reader is cautioned accordingly.

BIRD & BIRD

Bird & Bird is an international legal practice comprising Bird & Bird LLP and its affiliated and associated businesses. Bird & Bird LLP is a limited liability partnership, registered in England and Wales with registered number OC340318 and is regulated by the Solicitors Regulation Authority. Its registered office and principal place of business is at 15 Fetter Lane, London EC4A 1JP.

For details of Bird & Bird, our offices, our members, the use of e-mail and regulatory information, please see twobirds.com and, in particular, twobirds.com/english/Legal_Notices.cfm.

The word "partner" is used to refer to a member of Bird & Bird LLP or an employee or consultant, or to a partner, member, director, employee or consultant in any of its affiliated businesses, who has equivalent standing and qualifications. A list of members of Bird & Bird LLP and of any non-members who are designated as partners, and of their respective professional qualifications, is open to inspection at our London office address.

All such persons are solicitors, registered foreign lawyers or non-registered European lawyers.