This summer the Technology and Construction Court published its new Guidance Note on procedures for public procurement cases. The Guidance Note is broad in scope and covers much of the detail on the practical running of a procurement procedure, but a key focus is information – what should be disclosed, when it should be disclosed, and to whom it should be disclosed.
This requirement is relatively unique to challenges to procurement decisions because of the information imbalance between the procuring entity and the bidder. Very often, all the relevant documents sit with the authority – evaluation notes, meeting notes, the winning bidder's tender, information on matters discussed with the winning bidder, the form of the final contract... the list can go on, particularly if a long and complex procurement process has been undertaken. The Guidance Note looks at the practicalities of information provision both during the pre-action phase and once litigation has commenced.
What should the pre-action phase look like?
Due to the unique time pressure involved in procurement challenges, there is almost inevitably a flurry of correspondence between receipt of a standstill letter and the conclusion of the standstill period. The Guidance provides a shape for that correspondence:
That is broadly what happens in any event in most claims so doesn't significantly change the way things are generally dealt with. What is more interesting is the way the Guidance expects parties to act:
Information disclosure in the early stages of the procurement
The Guidance also looks at information provision in the early stages of the proceedings. It repeats that authorities should provide "key decision making materials" very early in proceedings or in pre-action correspondence, including the so-called 'procurement report' detailing key aspects of the process, and documentation that was kept to provide a written record justifying all the key decisions that were made.
Confidentiality
The Guidance is clear that confidentiality is not a bar to disclosure. However, it also recognises that some confidential information should be disclosed if appropriate within a confidentiality ring, established as early as possible. The participants in such a ring will vary, and indeed you may have two 'tiers' of participants in a ring, some of whom can see more information than others. That might include for example, only external lawyers being able to see some of the most sensitive information about the winning bidder, whereas other information could be shared with a 'clean team' within the claimant who will be separated from future business where the information might give them an advantage.
Conclusion
The extent to which public authorities act reasonably in providing information in procurement processes varies enormously in our experience. The Guidance settles firmly in favour of the provision of some key information at a very early stage. Whilst it is not binding, a failure to comply with it could have adverse cost consequences for an authority. For example, a court is likely to take into account the contracting authority's behaviour if a claimant needs to discontinue proceedings having obtained disclosure of documents it had rightly requested and should in accordance with the guidance have been provided with earlier. That said it is also worth noting that the Guidance requires a claimant also to act proportionately and reasonably, and that would undoubtedly include in respect of the scope of its requests.
For that reason, the Guidance is unlikely to resolve all skirmishes. Authorities are rightly concerned about maintaining the confidentiality of information, and want to avoid pandering to fishing exercises. In light of this, disagreements about what is relevant to any particular complaint, and what information a bidder is entitled to seem likely to continue.