This month, the court published the transcript of an early hearing in the Cemex v Network Rail dispute. It makes difficult reading for those considering challenging, reinforcing the tight 7-day statutory timetable for serving the particulars of claim and emphasising that it is important to tightly limit disclosure requests at an early stage.
Cemex bid for a contract to manufacture and supply Network Rail with railway sleepers. It was unsuccessful, losing to PCM RAIL.ONE AG which bid on the basis of an innovative, and much cheaper, system of sleeper manufacture. Cemex challenged on the basis that the tender was "abnormally low", with the case seeming to boil down to the fact that Cemex felt that the system RAIL.ONE was planning to use wasn't suitable for Network Rail's requirements.
The timelines for serving the particulars of claim in procurement cases are extremely short – only 7 days from the issue of the claim form. Cemex argued that without disclosure it could not properly plead its case and so applied, on day 7, for an extension of time. Hearing the application after the summer break, Coulson J concluded that the course Cemex chose was "risky" and that it was "not the sort of application that this court should encourage". He refused the application, and it appears to have been the agreement of the Defendant that Cemex could have a short period after the hearing within which to file their Particulars that prevented the claim being fatally undermined by the decision to seek an application to extend time.
The key points Coulson J made were that:
Coulson J's position in respect of number 3 appears to significantly undermine bidders' rights in challenges in the UK, and appears difficult to reconcile with EU law. A breach of the Treaty principles of equal treatment, non-discrimination and proportionality in particular, should not be judged on the same basis as a manifest error. An authority has no discretion in applying those Treaty principles – as Coulson J has concluded previously.[1] It appears to follow, therefore that it is not the case that "at all times…in a procurement challenge, the issue is limited to whether the contracting authority has made a manifest error…". We assume therefore that his comments were intended to relate to the sort of claim in front of him.
Coulson J suggests that it would have been preferable for Cemex to plead its case and use that pleading as the basis for an application for disclosure. Instead, it applied for specific disclosure only on the basis that it needed documents to plead its case – having conceded under pressure in the hearing that it did not need those documents and could plead without them, the application was left almost without purpose. The key points of the judge's decision were: